The repairs to Bertha, the Highway 99 Tunnel boring machine, will likely be more extensive than originally planned, a Washington State Department of Transportation official said on Thursday.
Seattle Tunnel Partners, the contractor digging the underground roadway has told WSDOT "verbally" that they are going to replace the machine's main bearing, according to Todd Trepanier, a program administrator for the department.
Until now, the contractor has only said that it would replace a set of damaged seals that protect the bearing. For weeks, Seattle Tunnel Partners has not confirmed whether the bearing itself might have been damaged by grit or water when the seals failed.
Some Rothe Erde bearings come equipped with monitoring systems and have measuring devices. WSDOT told Crosscut in early March that neither were installed on Bertha.
The machine is currently stopped near South Main Street, under Pioneer Square. It has barely moved in the last 117 days.
Bertha was first idled in early December after encountering increased resistance while digging. Seattle Tunnel Partners detected the bearing seal problems in late January.
The contractor has been working with the machine's manufacturer, Hitachi Zosen Corp., on plans to partially unearth and repair the tunneling rig. That operation will involve excavating an 83-foot diameter, 120-foot deep circular pit in between the Alaskan Way Viaduct and Pier 48, south of South Main Street. Before digging can begin, WSDOT and Seattle Tunnel Partners are awaiting the results of an archeological survey that is required to meet Federal Highway Administration cultural preservation guidelines.
An overhead view of the site where Seattle Tunnel Partners will dig a shaft to repair Bertha. Image: WSDOT
Trepanier could not give an updated time frame for the repairs. Seattle Tunnel Partners project manager Chris Dixon had said at the end of February that the machine might be boring again in about six months. He had called that estimate "slightly optimistic."
"We expect there will be some fine tuning to that," Trepanier said on Thursday, referring to Dixon's original repair time estimate. But he added, "I'm not seeing anything yet that makes me think it's going to be a big change."
Work is still underway at the tunnel site constructing an operations building and roadways at the south and north portals.
The tunnel will eventually replace the aging Alaskan Way Viaduct, which could fail in a major earthquake. Bertha is currently about 1,000 feet along the 9,300-foot tunnel path, which begins in Sodo and ends in South Lake Union. When the project began, the tunnel was scheduled to open in December 2015.
Under the terms of a contract between Seattle Tunnel Partners and Hitachi Zosen, until Bertha reaches 1,300 feet the contractor will not pay the manufacturer the final 10 percent of the cost for the nearly $90 million machine. As of Dec. 31, 2013, according to WSDOT, the state had paid Seattle Tunnel Partners $832 million. WSDOT has been adamant that the state's "design-build" contract will insulate taxpayers from any costs incurred because of the current delays and repairs.